Scrapbook Photo 03/25/24 - 93 New Stories - REAL Environmental & Conservation Leadership In PA: http://tinyurl.com/3729bhvv
Sunoco Fails To Meet July 1 Cleanup Deadline For Mariner East Pipeline Spill In The Lake At Marsh Creek State Park, Chester County
Photo

On August 2, Senator Katie Muth (D-Chester) and Rep. Danielle Friel Otten (D-Chester) announced Sunoco has failed to meet its July 1 deadline for cleaning up the Mariner East Pipeline spill into Marsh Creek Lake in Marsh Creek State Park in Chester County

August 10 marks the two-year anniversary of the spill, which sent more than 20,000 gallons of drilling mud into streams, wetlands, and the lake during construction of Sunoco’s Mariner East II pipeline.

A Consent Order and Agreement signed in December between the Department of Environmental Protection, the Department of Conservation and Natural Resources, and Sunoco Pipeline L.P., a subsidiary of Energy Transfer, required Sunoco to complete dredging, remove the dredged material to an approved disposal facility, and restore the access and staging areas on or before July 1, 2022.

In documents submitted to DEP on June 23 and July 7, Sunoco attributed its failure to meet the agreed-upon schedule to a number of factors, including weather, the presence of an unexpected amount of debris in the lakebed, and repeated significant equipment failures, including the July 1 failure of a containment bag at the sediment dewatering site.

The biggest delay was attributed to the company’s discovery of two existing pipelines under the area to be dredged, meaning that the planned mechanical dredging could not be completed safely, so divers were brought in.

“We are now more than one month past the deadline and two years past the spill and Sunoco has failed to complete the required remediation and restoration in the time frame agreed to,” Rep. Otten said. “The excuses for their delays are things they could and should have accounted for in their planning process -- especially the existence and location of two pipelines clearly visible on public maps to anyone with a browser and an internet connection.

“This operator continues to show absolute disregard for the people and communities impacted by their work,” said Rep. Otten.  “Senator Muth and I have met with DEP for updates on the project and have called on DEP to hold Sunoco accountable to the fullest extent possible for their ongoing delays.”

While Sunoco completed the removal of the top six inches of sediment from the affected portion of the lake in late July, allowing the 33-acre Ranger Cove section of Marsh Creek Lake to finally reopen to the public after nearly two years, cleanup and restoration of the sediment dewatering field, located in a neighborhood just outside Marsh Creek State Park, are still underway.

“Energy Transfer (Sunoco) continues to prove that they cannot operate responsibly in our commonwealth. After spilling over 20,000 gallons of industrial waste into Marsh Creek Lake, a drinking water supply for thousands of families, they have also failed to remediate and restore the lake and aquatic habitats by the required deadline of July 1," Sen. Muth said. "Further, they have failed to ensure clean drinking water for impacted residents whose private wells are irreversibly contaminated from other reckless operations during construction of the Mariner East II pipeline."

“I’m not surprised that Energy Transfer made sure to complete their pipeline in an expedited manner even with a mandated reroute. It is boldly clear that Energy Transfer doesn’t care and has never cared about anything other than ensuring their own profits even if it means harming our waterways and communities,” said Sen. Muth.

“They failed to complete remediation on time but forked over big cash to buy houses in the way of their cash cow to make sure that they could be fully operational by the end of the second quarter of this year," Sen. Muth added. "The powers that be in Harrisburg, on both sides of the aisle, have allowed corporate polluters to make our communities into sacrifice zones for the sake of shareholder wealth. If an entity can’t be an honest, respectful partner, they shouldn’t be allowed to do business in our Commonwealth.”

The Consent Order and Agreement gives DEP the ability to impose penalties of $10,000 per day for each day past the July 1 deadline and allows the department to exact more severe penalties as appropriate, up to and including the forfeiture of a $4 million surety bond posted by Sunoco at the outset of the agreement to ensure the performance of the company’s obligations.

In its settlement with DEP and DCNR, Sunoco agreed to dredge and remove contaminated sediment; replace damaged fish, wildlife, and turtle habits; and restore the shoreline and streamline buffers.

The company also agreed to pay $4 million to DCNR for improvements to the lake and park and $341,000 in DEP permit violations.

The settlement requires Sunoco to follow the agreed-upon Impact Assessment and Restoration Plan and restore the lake to “as good or better” than its condition prior to the August 2020 spill.

More information is available on DEP’s Mariner East Pipeline webpage.

Related Article - Criminal Charges:

-- AG Shapiro: Energy Transfer/Sunoco Convicted Of Criminal Charges Related To Construction Of Mariner East 2 & Revolution Natural Gas/Liquids Pipelines In PA  [PaEN]

Related Articles - Marsh Creek Lake Spill:

-- DEP Approves Sunoco's Mariner East Pipeline Marsh Creek State Park Lake Restoration Plan

-- Sunoco/Mariner East Pipeline To Pay $4 Million In Damages And Restore Lake At Marsh Creek State Park Polluted By A Spill In Chester County

-- DEP Orders Sunoco To Reroute 1+ Mile Of Mariner East Pipeline, Investigate Chester County Marsh Creek Lake Spill, Restore Impacted Resources

-- Mariner East Pipeline Drilling Stopped Indefinitely At Site Of Leak Into Marsh Creek State Park Lake, Chester County; Pipeline Company Will Be Held Accountable

NewsClips This Week - Oil & Gas:

-- Citizens Voice: Conventional Drilling Wastewater On PA Roads Dangerous To Human Health, Environment

-- Centre Daily Times: Study: Drilling Wastewater On PA Roads Dangerous To Human Health, Environment

-- Gettysburg Times: Study: Drilling Wastewater On PA Roads Dangerous To Human Health, Environment

-- Latrobe Bulletin: Study: Drilling Wastewater On PA Roads Dangerous To Human Health, Environment

-- Erie Times: Study: Spreading Drilling Wastewater On PA Roads Is Dangerous To Human Health, Environment

-- PA Capital-Star: Study: Drilling Wastewater On PA Roads Dangerous To Human Health, Environment

-- Environmental Health News: PFAS, With Possible Link To Oil & Gas Drilling, Found In Washington County Water Supply By University Of Pittsburgh

-- StateImpactPA - Rachel McDevitt: New PA Law Aims To Address Old Oil & Gas Well Cleanup, But It Could Make The Problem Worse, Critics Say; Wolf Launching Review Of Conventional Drilling Industry

-- KDKA: Parents Oppose Plans For Natural Gas Well Fracking Within 1,700 Feet Of Elizabeth Forward H.S. In Allegheny County

-- FracTracker Alliance: New Film Tells Story Of Grant Twp., Indiana County's Fight Against Fracking Waste & The Survival Of The Hellbender -- By Ted Auch, PhD

-- Post-Gazette - Anya Litvak: Can Environmental Violations Define Oil & Gas Companies As Bad Actors?  A Judgment Awaits

-- AP: Energy Transfer/Sunoco Pleads No Contest To Criminal Charges Related To Mariner East, Revolution Pipelines

-- WHYY: Energy Transfer Pleads No Contest To Criminal Charges Related To Mariner East, Revolution Pipelines

-- Post-Gazette - Anya Litvak: Energy Transfer Reaches Plea Deal With AG In Criminal Case Over Mariner East And Revolution Pipelines

Related Articles This Week - Oil & Gas:

-- AG Shapiro: Energy Transfer/Sunoco Convicted Of Criminal Charges Related To Construction Of Mariner East 2 & Revolution Natural Gas/Liquids Pipelines In PA  [PaEN]

-- DEP Invites Comments On Over 14 Miles Of 16-Inch & 24-Inch Natural Gas Gathering Pipeline Project In Susquehanna County [PaEN]

-- Conventional Oil & Natural Gas Drilling: An Industrial Machine Moving Across The PA Countryside Leaving Behind Big Liabilities & Spreading Pollution Everywhere It Goes  [PaEN]

-- DEP Inviting Stakeholders To Participate In Workgroups On New Federal Conventional Oil & Gas Well Plugging Program  [PaEN]

-- Environmental Health Project: Asthma And Air Pollution From Natural Gas Drilling/Facilities  [PaEN]

-- TribLive Guest Essay: EPA Must Address Natural Gas Leaks That Are Harming Our Children - By Kim Anderson, Evangelical Environmental Network  [PaEN]

-- Republicans On House Committee Disapprove Final Reg. To Reduce VOC/Methane Emissions From Unconventional Oil & Gas Facilities Risking $500 Million In Federal Highway Funds  [PaEN]

-- Evangelical Environmental Network Opposes House Resolution Disapproving Of Final Reg. Reducing VOC/Methane Emissions From Unconventional Oil & Gas Facilities  [PaEN]

-- Environmental Health Project: Public Health Impacts Of Blue Hydrogen Production, Health, Environmental Protections Needed -- By Alison L. Steele, Executive Director  [PaEN]

[Posted: August 4, 2022]


8/8/2022

Go To Preceding Article     Go To Next Article

Return to This PA Environment Digest's Main Page